Georgetown publishes its plan review windows, which makes the schedule unusually predictable, provided the application is accepted in the first place. Two things dominate the timeline here: the historic overlay districts, and the city's own electric utility.

  • Development Services · 406 W. Eighth St.
  • Portal: My Government Online (MGO Connect)

In review Cleared Correction return Submittal assembled, ready for intake.

T-101 · Published review windows

What the city publishes

These are Georgetown's own stated turnarounds, not our estimates. Every one of them starts when the application is accepted, which is a separate gate from submitting it.

Review typePublished windowMeasured from
Residential plan review15 to 20 business daysfrom the time the application is accepted
Commercial plan review30 business dayspublished turnaround
Certificate of Occupancy10 business daysfor zoning verification, fire and building review
Planning review rounds20 / 15 / 10 business daysfirst, second, third and subsequent rounds

Source: City of Georgetown Development Services and Development Manual (03.09.2026). Retrieved August 2026.

T-102 · Sequence

How the sequence stacks up

The same residential remodel, with and without a historic overlay. Both use Georgetown's own published review rounds. The difference is the Certificate of Appropriateness, which has to clear before the building permit clock starts.

Standard residential remodel 15-20 days
In a historic overlay district COA, then 15-20
Active review Queued Correction round

Source: City of Georgetown Development Manual, 03.09.2026, and residential permit pages.

N-101 · Local notes

What controls the schedule here

The requirements specific to this jurisdiction that cost the most when they surface late.

  1. Historic overlay review runs on a hearing calendar, not a review clock

    Projects in the Downtown or Old Town Overlay Districts, designated Historic Landmarks, and proposed demolition of historic structures require a Certificate of Appropriateness. Depending on scope, it is approved either administratively by the Historic Preservation Officer or by the Historic and Architectural Review Commission at a public hearing. HARC meets the second and fourth Thursday of each month at 6pm. New applications are accepted only two days per month, and fees must be paid by noon on the Friday following the deadline or the application is not filed. The building permit process begins only after the COA is approved.

  2. The city runs its own electric utility, and lead times are long

    A separate electric permit is required for service work. Service rebuilds need 48 hours' notice and two simultaneous inspection requests. Commercial submittals require proof of line extension submittal from Electrical Engineering. Where a line extension is needed, the city publishes that material lead times may exceed six months. Only one electric meter is permitted per residence, which affects accessory dwellings directly.

  3. Impervious cover is usually set at platting, not by a citywide table

    The allowed limit is frequently a note on the original subdivision plat; where it is not, the Unified Development Code governs. Swimming pools count at 50% of the water surface area. This is a site design constraint, and it is worth confirming before the civil set is drawn.

  4. There is no expedited review, and the city says so

    Georgetown states that it "does not offer an expediting option for plan review." The only available lever is a complete, correct application that clears in fewer rounds.

  5. Impact fees are substantial and separate from permit fees

    As of October 2023 the city published water impact fees of $11,000 and wastewater impact fees of $6,129 based on a 3/4-inch water meter. These are in addition to permit and plan review fees, and they belong in the pro forma early.

F-101 · Fees

How Georgetown calculates permit fees

City fees are separate from ours and are paid to the jurisdiction. Impact fees, where they apply, are separate again and are frequently the largest number on the page.

Permit typeFee basis
New single-family$125 application + $125 and $0.50 per sq ft permit + $25 technology
Residential remodel or addition$60 application + $60 and $0.50 per sq ft permit + $10 technology
Residential plan reviewNo fee for new residential up to two stories and four living units
CommercialICC valuation-based, $150 application + $50 technology; plan review is half the permit fee
Certificate of AppropriatenessHARC $505 · HPO $185 · Minor HPO $121
Heritage tree removal or pruning$606 standalone

Source: City of Georgetown Construction Fee Schedule, Rev 06.12.2026, and Planning Application Fee Schedule.

N-102 · Areas we work in Georgetown

  • Sun City
  • Wolf Ranch
  • Berry Creek
  • Georgetown Village
  • San Gabriel Village
  • Serenada
  • Heritage Oaks
  • Woodlake
  • La Conterra
  • River Chase
  • Mason Ranch

J-100 · Other service areas

T-001 · Transmittal

Have a project that needs a path forward?

Evaluating a site, working through entitlements, preparing an application, responding to comments, or trying to move a project that has stalled. Tell us where it stands and we will map what comes next.